Estate inspections feedback

Find out what we have done recently in your area as a result of our estate inspections.

Cleveleys

The Cavendish Mansions scheme inspection was completed on Monday 6th January 2025. The following issues were identified and actions taken.
Issues identified Action taken
No smoking sign missing — Block 1— 8  Requested replacement with Health & Safety
Untaxed vehicle in car park — block 9 — 18 Working with resident to remove this

 

The Cleveleys Estate inspection was completed on Monday 12th February 2024.  The following issues were identified and actions taken.
Issues identified Action taken
Several untidy gardens Contacted tenants directly
Grass verges on Tebay Avenue in poor condition Raised with Lancashire County Council

Over Wyre

 

The Over Wyre estate inspection was completed on Tuesday 10th December 2025. The following issues were identified and actions taken.
Issues identified Action taken
Roof tile slipped — Poppy Field Way, Pilling Raised job for repair
Fly tipping — Crooklands Gardens Residents spoken to and asked to remove items
Fence panel missing — Sandy Lane, Preesall Tenants advised Regenda not replacing at the moment
Untiday Garden — Preesall Letter sent to resident

 

 

The Barrington Close, Hambleton, estate inspection was completed on Tuesday 10th December 2025. The following issues were
identified and actions taken.
Issues identified Action taken
Hole in grassed area Rasied job for this to be filled
1 fence panel missing Fence panels not being replaced currently

 

Thornton

 

The Thornton estate walkabout was completed on Friday 21st February 2025.
The following minor issues were identified and actions undertaken
Issues identified Actions
Untidy gardens and bins on pavement on Knowsley Crescent Letters sent to residents to address this
Items left in garden on Prescot Place Letter sent to resident to address this
Untidy garden on Waring Drive Letter sent to resident to address this

 

The Thornton estate walkabout was completed on Tuesday 30th January 2024.
The following minor issues were identified and actions undertaken
Issues identified Actions
Several untidy gardens Spoke with residents and re-inspection arranged
Fence down around drying area near 22-27 Brays Heys Job raised
Grizedale Court - gutters need clearing Job raised
Pond identified at Flats on Knowsley Crescent Sent to asset management for assessment

 

Flakefleet

The Flakefleet estate walkabout was completed on Monday 26th February 2024. The following issues were identified and actions taken.
Issues identified Actions
General litter on the streets Reported to Wyre Council to ask them to clear
Several fence panels missing or sections of fence removed Regenda are not carrying out any fence repairs at the moment unless they are a health and safety risk
Fly tipping in alleyways Reported to Wyre Council 
Window smashed Reported to customer service centre

 

Rural

 

The Rural Estate walkabout was completed on Wednesday 27th November 2024. The following issues were identified and actions taken.

I ssue identified

Actions
7 Gardens in need of maintenance — 1 in Forton, 1 in Bilsborrow, 1 in Cabus, 1 in Catterall, 2 in Great Eccleston, 1 in Crossmoor. Letters sent to residents. 

 

The Rural Estate walkabout was completed on Wednesday 18th October 2023. The following issues were identified and actions taken.

Issues identified Actions
5 Gardens in need of maintenance Letter sent to residents.
Scheme in need of weeding and general grounds maintenance Job raised with grounds maintenance.

Warren Farm

The Fleetwood Town Centre Estate walkabout was completed on Tuesday 16th July 2024. The following issues were identified and actions taken.

Issues identified Actions Taken
Avon Green numerous weeds on pathway/parking area. Speak with Wyre council to see about de weeding/spraying. 
Silvia Way pot hole in the carpark. Raised with Lancashire County Council. 
Regenda land to the rear of Avon Green overgrown.  Raised with environmental team to see if this can be cleared. 
1 x Meter cupboard door come off at a property on Avon Green. Raised a job with M&Y. 
1 x Smashed window at a property on Hathaway Road. Spoken with tenant and raising a job for M&Y. 
6 x gardens in multiple areas in need of tidying. Letters sent to residents. 
Ariel Way, fridge/freezer fly tipped down the alleyway. Reported to Wyre Council. 

 

Fleetwood Town Centre

 

Balmoral Terrace scheme inspection were completed Monday 10th February 2025. The following issues were identified and actions taken.
Issues identified Action taken
Communal garden full of rubbish. Job raised for this to be cleared. 

Walmsley Street scheme inspection were completed Tuesday 4th February 2025. The following issues were identified and actions taken. 
Issues identified Action taken
1 x Item in communal bin store.  Job raised with Customer service centre for items to be removed.
1 x Chipped tile on step. Job raised with Customer service centre for this to be removed. 
1 x Guttering overgrown. Job raised with Customer service centre.
1 x  Internal communal area in need of a clean. Raised with Environmental team. 
1 x Lose guttering on one of the blocks. Job raised with Customer service centre. 
1 x Extractor fan vent come off. Job raised with Customer service centre.

Marine View scheme inspection were completed Monday 3rd February 2025. The following issues were identified and actions taken. 
Issues identified Action taken
Communal carpet in need of a clean. Raised with Environmental team.

Cherry Tree Court scheme inspections were completed on Thursday 30th January 2025. The following issues were identified and actions taken.
Issues identified Action taken
1 x item left outside block. Arrangements have been made to collect, checking again in 1 weeks time to make sure this has been removed.
1 x item left in communal area. Carded resident for this to be removed. 
1 x Bed frame in communal bin area. Spoken with resident who is removing this. 
1 x External gas meter cupboard door broken. Job raised with Customer service centre.

Mount Street scheme inspection were carried out Wednesday 29th January 2025. The following issues were identified and actions taken. 
Issues identified Action taken
1 x Alleyway full of rubbish Job raised for this to be cleared.

Church Street scheme inspections were completed Wednesday 29th January 2025. The following issues were identified and actions taken.
Issues identified Action taken
1 x Cable to front of property hanging down and needs fixing.  Job raised with Customer service centre.
1 x Vents need covering at the back of the block. Job raised with Customer service centre. 
1 x Hole left where a vent was at the back of one of the blocks. Job raised with Customer service centre.
1 x Sign missing from internal communal area.  To speak with Fire safety team to be replaced. 
1 x Internal area in need of a clean.  Raised with Environmental team.  
1 x Bike in communal area. Letter sent to the resident asking to remove. 

The Fleetwood Town Centre Estate walkabout was completed on Monday 13th May 2024. The following issues were identified and actions taken.
Issues identified Action taken
Lawrence Row guttering identified to be overgrown.  Raised a job for M&Y. 
Memorial Road guttering identified to be overgrown. Raised a job for M&Y. 
Lawrence Row fence panel out to the rear.  No fence panels being replaced at the moment. 

 

 

 

 

Poulton-le-Fylde

 

The scheme inspection for Carr Close, Poulton-le-Fylde was carried out on Thursday 6th February 2025.  There were no major issues identified. The following minor issues were identified and actions undertaken:
Issues identified Issues identified
Hallways need clearing Letter sent to all resident

 

The scheme inspection for Brockholes Crescent, Poulton-le-Fylde was carried out on Thursday 6th February 2025.  There were no major issues identified. The following minor issues were identified and actions undertaken:
Issues identified Actions
Fly tipping Job raised
Side gate broken Job raised
Drain to left side of property blocked Job raised
Dog fouling in the area Letter sent to all residents

 

The scheme inspection for Taylors Close, Poulton-le-Fylde was carried out on Thursday 6th February 2025.  There were no major issues identified. The following minor issues were identified and actions undertaken:
Issues identified Actions
1 x light out Reported to customer service centre

 

The scheme inspection for Greenway House, Poulton-le-Fylde was carried out on Thursday 6th February 2025.  There were no major issues identified. The following minor issues were identified and actions undertaken:
Issues identified  Actions
Bin area untidy Letter sent out to all residents  and job raised to clear

The Poulton-le-Fylde estate walkabout was completed on Tuesday 29th November 2022. There were no major issues identified. The following minor issues were identified and actions undertaken:

Issues identified Actions
Moss on pathways -  Elm Court Work completed
Fly tipping - Princess Avenue and Old Squire Close A job has been raised with our contractor to remove
Items being stored in Communal areas Letters have been sent to residents to request removal within two weeks
Pathways need clearing - Holts Lane Letters have been sent to residents to request removal within two weeks

 

Broadwater

The Broadwater Estate walkabout was completed Monday 15th April 2024. The following issues were identified and actions taken.

Issues identified                               

Actions
3 x Overgrown guttering on Cedar Avenue Job raised.
Exposed brickwork on Broadwater Avenue Job raised. 
Fencing down on Broadwater Avenue Raised job with M&Y to make safe.
6 Gardens in need of maintaining Letters sent to residents.

West View

The West View walkabout was completed Tuesday 10th October 2024. The following issues were identified, and actions taken.
Issues identified Actions taken
47 untidy gardens Spoken with all residents and will reinspect in two weeks.
8 cases of fly tipping Reported to Wyre council, M&Y and Environmental Warden to remove those that are on Regenda land.
4 issues with communal fencing. Environmental Warden to fix.

The West View walkabout was completed Tuesday 18th April 2023.
The following issues were identified, and actions taken.

Issues identified Actions
 Fly-tipping on St. John Avenue Enviromental warden and housing officer assisted with clearing and reported to the council. 
9 Untidy gardens Tenant have been contacted to maintain gardens and environmental warden assisting with clearing.
3 Communal blocks with faulty communal doors Jobs raised with customer service centre to be fixed.

 

Fylde

The Fylde walkabout was completed Monday 4th November 2024. 
Issue Actions
2 x Gardens in need of maintenance   Letters sent to residents.

 

Garstang

The Garstang estate inspections were completed on Tuesday 25th February 2025. The following issues were identified and actions taken.
Issues identified Actions taken
Several untidy gardens Contacted residents directly.

 

The Garstang scheme inspections were completed on Monday 24th February 2025. The following issues were identified and actions taken.
Issues identified Actions taken
5-8 Bluebell Way — Slippery path to the side of the block of flats. Job raised with Environmental team to be cleaned. 
51-53 Maple Road — Car parking sign post fallen down. Job raised with Customer service centre. 
9-35 Maple Road — Overgrown trees from private industrial estate on our land.  Job raised with Environmental team to be cut back.
51-57 flats on Windsor Road — corridors in need of a clean. Letters sent to the residents to address this. 
39-49 Windsor Road — Possible roof leak and ceiling still requires painting once all roof works have been completed, water pooling on pathway to the rear of the block.  Job raised with Customer service centre.